December 22, 2008

Bathroom Counter tops installed


















































Kitchen Counter tops installed




































































































December 15, 2008

















Interior wall and ceiling painting begun:
Harmony Interior Latex by Sherwin Williams-
zero VOC, low odor and Greenguard certified.

December 9, 2008

Installation of cabinets nearly complete. Countertop measurements made

Unit 3






























Unit 2



































Unit 1


































December 2, 2008

















Cabinet Installation































November 21, 2008
















color coat applied






























November 11, 2008
















brown coat goes on...



















































Skim coat applied to drywall - unit 1





















































October 29, 2008
















































































Sheathing for undersides of carport and decks: rolled steel sheets to be cut and "tiled"





















The first of the cabinetry goes in


















































October 22, 2008
















The kitchen cabinets coming together in the shop.
Domestic walnut veneer - oiled.




































October 21, 2008




















Unit 1: Gas Fireplace installation